3For execution of enabling works (Civil and E and M) from End of EPE to End of Shatabdi Nagar Station (Ch 33100 to 63450 m) section of Delhi - Ghaziabad - Meerut RRTS Corridor.
Agency :
National Capital Region Transport Corporation Limited
5Carrying out initial pile load test in the section from Sarai Kale Khan to Anand Vihar and connecting line from Sarai Kale Khan to Stabling Yard at Jungpura for Delhi-Ghaziabad-Meerut Regional Rapid Transit System (RRTS) Corridor.
Agency :
National Capital Region Transport Corporation Limited
6Supply, Installation, Commissioning and Maintenance of CORS (Continuously Operating Reference stations) Network including Server with Software and Supply of Rovers and setting up of reference points
Agency :
National Capital Region Transport Corporation Limited
7Construction of Foot over bridge (FOB) at various locations from Ghaziabad (Meerut Tiraha) to Meerut Bypass along the alignment of Delhi - Ghaziabad-Meerut RRTS Corridor
Agency :
National Capital Region Transport Corporation Limited
9Shifting / Modification of Electrical Utilities of 33kV, 11kV, LT Lines, Transformers etc. of PVVNL, infringing Delhi - Ghaziabad - Meerut RRTS Corridor of NCRTC (Chainage 75700 to 82800) (Meerut By pass (Near Modipuram Flyover) to Modipuram Depot)
Agency :
National Capital Region Transport Corporation Limited